The deployment of plant and technology at remote sites in Africa is prone to logistics complications, delivery delays and support problems yet, AngloGold Ashanti’s Geita Gold Mine in Tanzania is becoming a model of productivity in spite of these challenges.

Background

In 2006, decreasing production at the mine prompted AngloGold Ashanti to investigate and to make some hard business decisions. “The loss of skills at all levels throughout the process plant necessitated the implementation of automated control as far as possible to reduce variability and increase control expertise,” says Corné Lourens, Metallurgical Manager at Geita Mine.

AngloGold Ashanti decided to call in system integrator Systems Anywhere who had previously successfully addressed such problems for the company.

“One of the first things we found was a control system installation that required significant improvement in order to handle the higher level of automation that the client was looking for,” says Systems Anywhere MD, André Vuilleumier. “Some areas like switch gear configuration, did not conform with AngloGold’s normal practices; an example in this plant was that a running motor was shown in red because it indicated a hazard but a stopped motor was green because it was in a safe mode.” This contradicted Anglo’s normal standard indicators. With the skills shortage and high staff turnover the mining industry is experiencing, a standardised control philosophy would be key to consistent control and smoother operations.”

While upgrading the control system and improving the SCADA the project goals included:

  • Applying the corporate standard
  • Standardising the control philosophy
  • Improving the alarming and alarm logging for analysis
  • Maintaining a history of production data
  • Providing for real time and scheduled reporting and the production of those reports
  • Implementing an Expert System based on fuzzy rules to reduce process variation and improve production.

This was to be implemented using the latest technology while also providing for a maintenance plan and 24/7 support of the control system software in spite of the remoteness of the site.

“The fuzzy logic rules can and are implemented remotely from South Africa or anywhere else, saving time as well as transportation and consultation costs. The benefit of fuzzy logic rules will increase in parallel with the increase in unit run time, as well as compound its improvement as variability is decrease”
– Corn Lourens, Metallurgical Manager, Geita Gold Mine

Solution implementation

The software solutions chosen for the Geita Mine included an Expert System to be developed by Systems Anywhere which would run with Wonderware’s Information Server, Active Factory reporting tool, InTouch SCADA and Wonderware Historian, all hosted by Wonderware’s System Platform based on ArchestrA technology. Seventeen Allen Bradley PLCs would be upgraded to cope with the new environment.

“In order to make sure the customer got what was needed and to clarify the system design, we spent a lot of time on the User Requirement Specification,” says Vuilleumier. “We addressed everything from colour coding to access levels and implementation deployment schedules during planned maintenance stops to avoid unnecessary downtime. This was followed by a thin-slice simulation which was approved by the client.”

Part of the design was to keep all display screens as uncluttered as possible while providing operators with the drill-down facilities necessary to view any level of detail. “This is especially true of the alarms,” says Vuilleumier. “With ArchestrA, alarm groupings and the alarm tree are automatic and we only show the alarms that are relevant to the section being monitored, such as the ball mill. Then, using a Pareto chart, only the top ten alarms that must be serviced are displayed and the system logs who acknowledged each alarm. Previously, the unscreened flood of alarms meant that they were largely ignored.”

According to Vuilleumier, a discipline whereby the maintenance team effectively and regularly attends to the top three alarms in the Pareto chart can result in significant improvements in plant productivity.
Details on analogue alarms and values can be accessed using the same drill-down facility and performance trends can be examined through historical analysis to help predict potential problems on various items of plant – a key feature when spares availability is limited because of the remoteness of the site.

Expert System

An expert system can be defined as an operator who is always present, adheres to a control philosophy and maintains it at all times. In this case, such an expert operator needs to monitor the mill load, mill feed, power consumption, trends, etc. and then make a decision on whether to increase or decrease the input feed rate. In other words, this is a multi-variable control system which is quite different from the standard PID configuration.

The Expert System takes over the responsibility of changing the set points from the operator and brings the mill to peak performance by:

  • Filtering the process variables individually through a moving average and checking them against their parameters
  • Comparing the result of each variable against the rules that are stored in the database and analysing the result to determine whether the set point needs to be increased or decreased
  • Applying a time interval that determines how quickly it needs to react to the rule to ensure that production is kept consistent. It’s important to bear in mind that, in this environment, quick reactions times are essential but then processes need some time (10 to 30 minutes) to settle before any further corrective action is taken

“One of the benefits of this approach is its transparency and simplicity,” says Vuilleumier. “Complicated mathematics could be difficult to manage at site level whereas the fuzzy-based rules are more easily traced so that operators can understand the control philosophy of the system.”

Information delivery

The Wonderware Information Server facilitates the aggregation of large amount of plant data into highly informative production reports tailored to AngloGold Ashanti corporate requirements. This allows management to access the information from site and contribute towards improving their performance.

The Wonderware Information Server is integrated with the company’s existing IT infrastructure and web portals and has helped connect plant personnel so that they can access the entire plant record. Lab data can be manually entered when results are received and it is synchronised in the Historian at the time the sample was taken. Individual users at Geita Mine have been assigned access to different views/areas beyond their normal scope to allow them to do their jobs more effectively. Displays include KPIs, production reports, trends and published InTouch screens and any information is available in one or two seconds. “Reporting options are unlimited,” says Vuilleumier,

Benefits

The project spanned 12 months and the changeover occurred on a live plant during maintenance shutdowns. Realised benefits include:

  • The implementation of corporate standards
  • A new roadmap for future projects
  • A state-of-the-art control system with best support and training infrastructure
  • Greatly improved alarming – ensuring safety and logging the triggers
  • The right information allows the right people to improve plant performance even when not on site
  • Identification of bottlenecks (e.g. problems with the discharge dilution density)
  • Full remote support and fuzzy logic rule changes promote rapid improvements

“The production rate of the plant will benefit significantly from the upgrade” says Vuilleumier. “Other AngloGold Ashanti sites have benefited similarly in the past and by identifying the bottlenecks at Geita, we are aiming to improve recovery time and throughput.”

“The Wonderware Information Server gets the right people the right information at the right time so that they can improve plant performance even when not on site.”
– Andr Vuilleumier, MD, Systems Anywhere

AngloGold Ashanti

About AngloGold Ashanti’s Geita Gold Mine

Geita first came into prominence as the site of a German colonial gold mine. A German gold prospector discovered the mineral in the early 1900s in the hills surrounding modern-day Geita town.

This and other discoveries triggered a gold rush in the surrounding area, attracting German and native prospectors alike. The colonial government established a mine to exploit ‘Bismarck Reef’.

Mining activities significantly declined, however, when Germany ceded control of its colonies to the British after their defeat in World War I.

Geita regained its prominence in the mid to late 1990s when the Tanzanian government opened the mineral sector to foreign investment. A number of medium to large-scale mining houses, including Ashanti and Anglo American, conducted extensive exploration activities in the surrounding areas.

The most significant outcome of these developments was the construction of the open-pit Geita Gold Mine, now owned by AngloGold Ashanti and the largest gold producer in Tanzania.

Source Wikepedia